Health Professions Building 1 (Willow Hall)

Programmer: Facility Programming and Consulting
Architect: Barnes, Gromatzky, Kosarek
Total Project Cost (DD): $67,500,000
Total Project Cost (CIP): $67,500,000
Contractor CM@R:  HCBeck, Ltd
Design Development Approval: May 2016 (Actual)
GMP Approval: August 2016 (Actual)
Construction Start: September 2016 (Actual)
Construction Completion: Spring 2018 (Projected)
Occupancy: Spring 2018 (Projected)

The Health Professions Building 1 (Willow Hall) has a total project cost of $67.5 million at a total size of 107,708 gross square feet. Occupancy is targeted for May 2018 to accommodate use by the first cohort of students by June 1, 2018.

Status:  Construction is approximately 28 percent complete and is on schedule.

Web Cam/ Public Link: http://www.facilities.txstate.edu/pdc/Project-Live-Feed.html

Next Milestone: Permanent power is the next major milestone for July 2017.