Health Professions 1

Willow Hall

(Health Professions Building 1)

Programmer: Facility Programming and Consulting

Architect: Barnes, Gromatzky, Kosarek

Total Project Cost (DD): $67,500,000

Total Project Cost (CIP): $67,500,000

Contractor CM@R: HCBeck, Ltd

Design Development Approval: May 2016 (Actual)

GMP Approval: August 2016 (Actual)

Construction Start: September 2016 (Actual)

Construction Completion: Spring 2018 (Projected)

Occupancy: Spring 2018 (Projected)

Willow Hall (The Health Professions Building 1) has a total project cost of $67.5 million at a total size of 107,708 gross square feet. Occupancy is targeted for May 2018 to accommodate use by the first cohort of students by

June 1, 2018.

Status. Construction is approximately 77 percent complete and is on schedule.

Milestone: Substantial Completion in March 2018 the next major milestone.