Skip to Content

Health Professions 1

Willow Hall            
Programmer: Facility Programming and Consulting    
Architect: Barnes, Gromatzky, Kosarek
Total Project Cost (DD): $67,500,000
Total Project Cost (CIP): $67,500,000    
Contractor CM@R: HCBeck, Ltd
Design Development Approval: May 2016 (Actual)
GMP Approval: August 2016 (Actual)
Construction Start: September 2016 (Actual)
Construction Completion: March 2018 (Actual)
Occupancy: May 2018 (Actual)

Willow Hall (The Health Professions Building 1) has a total project cost of $67.5 million at a total size of 107,708 gross square feet. Occupancy is targeted for May 2018 to accommodate use by the first cohort of students by
June 1, 2018.

Status.  Construction is complete.  Two existing academic departments from San Marcos will be moving in the new space.  The third will move in August 2018.  Occupancy is May 2018 to accommodate use by the first cohort of students by June 1, 2018.

Next Milestone: Close-Out Phase is the next milestone.