Skip to Content

Albert B. Alkek Library Learning Commons

Albert B. Alkek Library Learning Commons

Feasibility Study: Perry Dean Rogers

Programmer: Facility Programming and Consulting

Architect: Brown Reynolds Watford, Dallas, TX

Total Project Cost (CIP): $12,612,894

Total Project Cost (DD): $8,300,000

Contractor CM@R: JE Dunn Construction, Austin, TX

Design Development Approval: August 2018

GMP Approval: November 2018 (Projected)

Construction Start: November 2018 (Projected)

Construction Completion: February 2020 (Projected)

Occupancy: Spring 2020 (Projected)

 

The Albert B. Alkek Library Learning Commons has a total project cost of approximately $8.3 million for Phase One to re-purpose space for creation of a Learning Commons on the second floor, and portions of the first, third, and fourth floors of the Library.

 

Status: The Albert B. Alkek Library Learning Commons has a total project cost (TPC) of approximately $8.3 million for Phase One and is on the current Capital Improvements Program (CIP) at $12,612,894. The scope of work includes the repurposing of space for creation of a Learning Commons on the second floor, and portions of the first, third, and fourth floors of the Library. Brown Reynolds Watford, Dallas, TX, is the design architect and JE Dunn Construction, Austin, TX, is the Construction Manager at Risk. The design phase is underway.

 

Next Milestone: The next milestone is to begin reviewing the Schematic Design solutions.