Albert B. Alkek Library Renovations

Albert B. Alkek Library Renovations

Feasibility Study: Perry Dean Rogers
Architect: PBK Architects
Total Project Cost (DD): $14,024,925
Contractor CM@R: Vaughn Construction
Design Development Approval: May 2015
GMP Approval: August 2015 (Actual)
Construction Start: September 2015 (Actual)
Construction Completion: June 2017 (Actual)
Occupancy: Spring 2017 (Actual)

The Albert B. Alkek Library Renovations project includes the phased repairs and upgrades of electrical and information technology systems, and limited mechanical infrastructure components.  Additional work is underway to remove and replace the lower level roofs which extended the completion date to June 2017. 

 Status:  The additional work to remove and replace the lower level roofs is 99 percent complete.  Substantial completion is pending formalized submittal for signature.

Next Milestone: Final Close-Out report to be issued to the System office in August 2017.