Skip to Content

Campus Recreation Sports Fields

Campus Recreation Sports Fields

Programmer: NA
Architect: Perkins Will (Sink Combs Dethlefs); Denver
Total Project Cost (DD): $7,400,000
Total Project Cost (CIP): $3,000,000
Contractor CSP:  TBD
Design Development Approval:    February 2018 (Actual)
CSP Approval: September 2018 (Projected)
Construction Start: October 2018 (Projected)
Construction Completion: Spring 2019 (Projected)
Occupancy: Spring 2019 (Projected)

The Feasibility Study for the development of the new multi-use Campus Recreation Sports Fields resolved basic inquiries regarding options for developing natural grass recreation playfields on a site previously used as the University‚Äôs golf course.  The Golf Pro-Shop wood structures were removed and a structural analysis was completed which determined that the historic stone shell of the building was stable for repurposing.  That structure is now completed and in use.  

Status:  Sink Combs Dethlefs Architects of Denver, Colorado, completed the Design Approval Binders. The design approval was formalized at the February 2018 Board of Regents meeting with a TPC of $7.4 million.  Coordination efforts with the Center for Archeology Studies are complete.  TSUS is negotiating a revised contract with the A/E to proceed into the construction documents phase.  Construction to start in October 2018.

Next Milestone:  The next milestone will be the production of the Construction Documents.