Skip to Content

Bruce and Gloria Ingram Hall

Bruce and Gloria Ingram Hall

Programmer: Facility Programming and Consulting
Architect: Treanor Architects
Total Project Cost (DD): $120,000,000
Total Project Cost (CIP): $120,000,000
Contractor CM@R: SpawGlass Construction
Design Development Approval: May 2016 (Actual)
GMP Approval: July 2016 (Actual)
Construction Start: August 2016 (Actual)
Construction Completion: Summer 2018 (Projected)
Occupancy: Fall 2018 (Projected)

The Engineering and Science Building (Bruce and Gloria Ingram Hall) TPC is $120 million at a total size of 166,851 gross square feet.

Status:  Construction is approximately 25 percent complete and is on schedule.  Occupancy is targeted for July 2018 to accommodate students by August 2018.

Next Milestone: The CMR will continue with underground site utilities construction in May/June 2017.

The clickable link for the live-camera is located at:  http://www.facilities.txstate.edu/pdc/Project-Live-Feed.html