Skip to Content

Bruce and Gloria Ingram Hall

Bruce and Gloria Ingram Hall
Programmer: Facility Programming and Consulting    
Architect: Treanor Architects
Total Project Cost (DD): $120,000,000
Total Project Cost (CIP): $120,000,000    
Contractor CM@R: SpawGlass Construction
Design Development Approval: May 2016 (Actual)
GMP Approval: July 2016 (Actual)
Construction Start: August 2016 (Actual)
Construction Completion: Summer 2018 (Projected)
Occupancy: Fall 2018 (Projected)

Bruce and Gloria Ingram Hall (The Engineering and Science Building) TPC is $120 million at a total size of 166,851 gross square feet.  

Status:  Construction is approximately 78 percent complete and is on schedule.  Recent design deficiencies were identified on the project and are now being remediated. Occupancy is targeted for July 2018 to accommodate students by August 2018.

Next Milestone: The CMR will continue with underground site utilities construction.