Skip to Content

Bruce and Gloria Ingram Hall

Bruce and Gloria Ingram Hall

Programmer: Facility Programming and Consulting
Architect: Treanor Architects
Total Project Cost (DD): $120,000,000
Total Project Cost (CIP): $120,000,000
Contractor CM@R: SpawGlass Construction
Design Development Approval: May 2016 (Actual)
GMP Approval: July 2016 (Actual)
Construction Start: August 2016 (Actual)
Construction Completion: Summer 2018 (Projected)
Occupancy: Fall 2018 (Projected)

Bruce and Gloria Ingram Hall (The Engineering and Science Building) TPC is $120 million at a total size of 166,851 gross square feet.  

Status Construction is approximately 93 percent complete and is on schedule.  Recent design deficiencies were identified on the project and are now being remediated. Partial occupancy is targeted for July 2018 to accommodate classes by August 2018.

Next Milestone: The CMR will continue with underground site utilities construction.