Programmer: VisSpiro Strategies
Architect: Lym Miller Architects, Austin, TX
Total Project Cost (DD): $3,416,000
Total Project Cost (CIP): $3,500,000
Contractor CMR: TBD
Design Development Approval: NA - Delegated Authority
GMP Approval: September 2019 (Projected)
Construction Start: September 2019 (Projected)
Construction Completion: July 2020 (Projected)
Occupancy: August 2020 (Projected)

Jowers Center Renovation.  The Department of Athletics will relocate its offices and other functions from Jowers Center to the newly expanded University Events Center in summer 2018. The vacated space in Jowers Center is needed for the degree programs in the Department of Health and Human Performance and for the Dance program in the Department of Theatre and Dance.  Renovated space will be used for faculty offices, classrooms, and laboratory/research space.

Status:  Programming by VisSpiro Consultants is complete; and the TPC of this 13,561 GSF renovation project is $3.416 million.  The university has received delegated authority for this renovation.  The contract for the A/E is under negotiations.  The RFQ CMR is posted.

Next Milestone: The next milestone will be the design beginning in August 2018.