LBJ Student Center Renovation

LBJ Student Center Renovations

Programmer: Facility Programming and Consulting
Architect: Atkins Architects/Engineers, Austin
Total Project Cost (DD): $20,070,000
Total Project Cost (CIP): $20,113,150
Contractor CM@R: Vaughn Construction, San Antonio
Design Development Approval: August 2016 (Actual)
GMP Approval: November 2016 (Actual)
Construction Start: December 2016 (Actual)
Construction Completion: May 2018 (Projected)
Occupancy: Summer 2018 (Projected)

The scope of work on the LBJ Student Center Renovation includes repairs and upgrades of the infrastructure components and incidental interior/exterior renovations and repairs.

Status:  Construction is underway and is approximately 30 percent complete.  The anticipated completion date is May 2018.

Next Milestone: Fire Alarm System test and approval in September 2017 is the next construction milestone.