RRHEC #2- Nursing Building

Programming:  Broaddus & Associates  
Architect/Engineer: Barnes Gromatzky Kosarek Architects &
 Richter Cornbrooks Gribble
Total Project Cost: $36,000,000 (BOR approved DD)
Gross Square Feet: 79,533 
CM@Risk Contract Award: January 2008 (Flintco, Inc.)
Design Development Approval: August 2008 
GMP Approval: December 2008 - May 2009  
Construction Start / Completion: January 2009 / May 2010 (Projected) 
Occupancy: August 2010 (Fixed)
 
The new Nursing Building will be the second academic building at the RRHEC campus. Following the campus master plan, it will be four floors containing lecture halls, classrooms, offices, high tech labs, exam rooms, and supporting facilities. The Design Development documents and project budget were approved at the Board in August 2008. To facilitate the compressed schedule, construction was to be undertaken in two stages with two GMP packages. Construction was initiated in January 2009 with approval of the site/foundation GMP package.    

Status: Construction is 45% complete.

RRHEC: Nursing Building
Artist rendering
Aerial photo of construction site
Photo: Nursing building under construction
Photo: Nursing building under construction
Photo: Nursing building under construction