Summary: Architectural/engineering programming
Programmer: Pfeiffer Partners Inc. (appointed February 2006)
Architect: TBD
Construction Manager at Risk: n/a
Total Project Cost Estimate: 59,405,654 ($300,000 feasibility study complete)
Funding Source: TBD
Occupants: Music, Theater and Dance
Start: TBD
Finish: TBD
Status: Concept design complete
The programming and feasibility study by Pfeiffer Partners, Inc. (Architects) was completed and the results presented to the Board in February, 2007. Initiation of the project design phase is dependent on securing sufficient funds. An independent current cost analysis is scheduled to be completed summer 2008 in a timely manner prior to the fiscal year of submission of anticipated TRB funding. Once funded, a parking garage and adjacent streets/site improvement projects will also be initiated.