Summary: New 94,419 gross square foot two-level expansion including a natatorium with two pools, rock climbing facility, exercise studios and fitness area, expanded basketball, volleyball and indoor soccer courts. Renovations and alterations of current 10,127 gross square foot facility
Architect / Engineer: Marmon Mok
Total Project Cost: $31,175,408
Gross Square Feet: 94,419
Design Development Approval: August 2006
CM@Risk Contract Award: September 2006 (
GMP Approval: May 2007
BOR Budget Re-approval: May 2007
Construction Start: July 2007
Occupancy / Completion: October 2008 / March 2009 (Projected)
Percent Complete: 30%
The