DHRL: Retama Residence Hall Renovations

Retama Residence Hall Renovations

Programmer: Facility Programming and Consulting
Architect: KSQ Architects
Total Project Cost (DD): $10,937,378
Total Project Cost (CIP): $9,026,199
Contractor CM@R: Flynn Construction
Design Development Approval: February 2016 (Actual)
GMP Approval: April 2016 (Actual)
Construction Start: May 2016 (Actual)
Construction Completion:  July 2017 (Projected)
Occupancy:  August 2017 (Projected)

The Retama Hall Renovations project has a TPC of $9 million.

Status: Construction is underway with substantial completion anticipated by summer 2017.  The project is approximately 89 percent complete.

Next Milestone: Substantial Completion is targeted for July with occupancy in August 2017.