Tomas Rivera Drive Relocation and Student Center Drive Realignment

Summary: Relocation of Tomas Rviera Drive to eastern side of the Student Health Center and realign of  Student Center Drive

Architect/Engineer: Halff Associates
Total Project Cost Estimated Total Project Cost: $8,371,938 (BOR Approved DD)
Contractor (CM@R):
SpawGlass Construction
Status: Final review of the construction documents is in progress.

The Board approved the selection of TBG Partners of Austin in November 2005 to perform a feasibility study and develop preliminary plans for the complex street and utility project. An independent traffic study was completed and the City of San Marcos acceptance of the street project as designed was achieved. Halff Associates was selected as the A-E to complete the design of the project. SpawGlass was selected as the CM@R. The new A/E and CM@R identified various additional scope issues related to multiple necessary utility relocations, traffic and phasing of elements of adjacent projects. The final Design Development package was approved by the Board in February 2008. Final review of the design is in progress and the CM@R is developing a GMP for approval to proceed with phased construction.

This project is an integral part of the North Campus Enhancement (NCE) package. It supports traffic and utilities relocation for the North Housing, the Matthews Parking Garage and the Cogen Expansion projects.