Summary: New west campus parking garage with a minimum of 721 parking spaces, landscape garden, bus shelters and pedestrian connection to Read Street/Student Recreation Center.
Architect / Engineer: Carl Walker, Inc.
Total Project Cost: $14,938,183
Parking Spaces: 721
Design Development Approval: August 2006
BOR Budget Re-approval: February 2007
CSP Contract Award: April 2007 (Vaughn Construction)
Construction Start: May 2007
Occupancy: July 2008 (Projected)
Percent Complete: 80%
The Speck Street Garage project is to create a minimum of 721 spaces in a structured parking garage meeting the design guidelines of the Campus Master Plan and current building and accessibility codes. Additionally, the project will include: 1) pedestrian connector walkway to Read St. along