University Events Center Expansion

University Events Center Expansion

Feasibility Study: Moody Nolan
Programmer: Facility Programming and Consulting
Architect: Sink Combs Dethlefs
Total Project Cost (DD): $62,500,000
Total Project Cost (CIP): $54,090,000
Contractor CM@R: Turner Construction
Design Development Approval: August 2016 (Actual)
GMP Approval: September 2016 (Actual)
Construction Start: September 2016 (Actual)
Construction Completion: September November 2018 (Projected)
Occupancy: October December 2018 (Projected)

This 81,282 gross square foot expansion includes space for commencement ceremonies and athletic programs.  The project also includes a new chilled water plant, a new loading dock, access to the lower court level, a multi-purpose suite, locker rooms, and offices.

Status: Construction is underway and is approximately 15 percent complete and the schedule is being tested by a significant delay in steel availability as a result of Hurricane Harvey.

Next Milestone: Structural frame topping out in November 2017 is the next major milestone.