University Events Center Expansion

University Events Center Expansion

Feasibility Study: Moody Nolan

Programmer: Facility Programming and Consulting

Architect: Sink Combs Dethlefs

Total Project Cost (DD): $62,500,000

Total Project Cost (CIP): $54,090,000

Contractor CM@R: Turner Construction

Design Development Approval: August 2016 (Actual)

GMP Approval: September 2016 (Actual)

Construction Start: September 2016 (Actual)

Construction Completion: November 2018 (Projected)

Occupancy: December 2018 (Projected)

 

The University Events Center project with a scope of work that also includes a new chilled water plant, a new loading dock with access to the lower court level, a multi-purpose suite, locker rooms, and offices, has a TPC of $62.5 million and the total size of the expansion is 81,282 GSF. The expansion includes space for commencement ceremonies and athletic programs.

 

Status: Construction is approximately 55 percent complete. Occupancy is targeted for fall 2018. The start-up of the new Chiller Plant is scheduled for January 2018.

 

Next Milestone: Drying-in the building by February 2018 is the next major milestone.

 