Summary: provides for the expansion of existing chilled water capacity meeting an immediate need with regards to improving system reliability and capability to handle future load growth on campus.
Architect / Engineer: Jacobs/Carter Burgess, Inc.
Total Project Cost Estimate: $ 9,613,406
Additional Capacity: 2,000 Tons
Design Documents Approval: October 2006
CM@Risk Contract Award: April 2007 (Spaw Glass)
BOR Budget Re-approval: June 2007
GMP Approval: July 2007
Construction Start: September 2007
Occupancy: December 2008 (Projected)
Status: 45% Complete
As part of the North Campus Enhancement package, the Cogeneration Plant Expansion project