Skip to Content

Blanco Hall Renovations

Blanco Residence Hall Renovations

Programmer: Facility Programming and Consulting
Architect: Pfluger Architects
Total Project Cost (DD): $29,600,000
Total Project Cost (CIP): $28,000,000    
Contractor CM@R: SpawGlass Construction
Design Development Approval: November 2017 (Actual)
GMP Approval: December 2017 (Actual)
Construction Start: December 2017 (Actual)
Construction Completion: July 2019 (Projected)
Occupancy: August 2019 (Projected)

The TPC for this phased project is $29.6 million. The scope of work for this comprehensive renovation includes new air handling units, new pumps, and new fan coil units.  In addition to cleaning the existing air ducts in the lobby; refurbishing select air handling units; replacing plumbing in the vertical chases, domestic water piping, sewer piping, and water closets; and relocating electrical distribution panels.  There are significant cosmetic improvements throughout the building such as installing new light fixtures in the corridors, bedrooms, bathrooms, and portions of the lobby.

Status:  Pfluger Associates is the A/E, and SpawGlass is the CMR. The project is 49 percent complete and substantial completion is expected in summer 2019.

Next Milestone: The next milestone is Substantial Completion of Wing B.