Elliott Hall Repurposing

Programmer: VisSpiro Strategies    
Architect: LPA Architects, San Antonio, TX
Total Project Cost (DD): $6,650,000
Total Project Cost (CIP): $6,650,000    
Contractor CMR: TBD
Design Development Approval: November 2018 (Actual)
GMP Approval: January 2019 (Projected)
Construction Start: March 2019 (Projected)
Construction Completion: Spring 2020 (Projected)
Occupancy: Spring 2020 (Projected)

Elliott Hall, which opened in 1963, is located next to McCoy Hall and has three freestanding buildings that were used for student housing and community and administrative functions. The project will repurpose all three buildings for classrooms and faculty offices, totaling 37,293 GSF at a TPC of $6.65 million.   

Status:  LPA Architects of San Antonio, is the selected design team and Hill & Wilkinson General Contractors of Austin, is the Construction Manager-at-Risk. The project was approved at the November 2018 Board meeting.  The Design Phase is nearing completion.  The GMP is being reviewed for approval and the Construction Phase will begin in March 2019.

Next Milestone: The next milestone is the Construction Notice to Proceed (NTP).