Elliott-Hall-Repurposing

Elliott Hall Repurposing

Programmer: VisSpiro Strategies    
Architect: LPA Architects, San Antonio, TX
Total Project Cost (DD): $6,650,000
Total Project Cost (CIP): $6,650,000    
Contractor CMR: TBD
Design Development Approval: November 2018 (Projected)
GMP Approval: December 2018 (Projected)
Construction Start: December 2018 (Projected)
Construction Completion: Spring 2020 (Projected)
Occupancy: Spring 2020 (Projected)

Elliott Hall, which opened in 1963, is located next to McCoy Hall and has three freestanding buildings: two for student housing and one for community and administrative functions. The project will repurpose all three buildings for classrooms and faculty offices, totaling 37,293 GSF at a TPC of $6.65 million.   
Status:  LPA, Inc. is the selected A/E, and Hill Wilkinson General Contractors is the CMR. Design is final and the project is on the agenda for BOR approval in November 2018.

Next Milestone: The next milestone will be the start of construction.