Skip to Content

Bruce and Gloria Ingram Hall

Bruce and Gloria Ingram Hall

Programmer: Facility Programming and Consulting    
Architect: Treanor Architects
Total Project Cost (DD): $120,000,000
Total Project Cost (CIP): $120,000,000    
Contractor CM@R: SpawGlass Construction
Design Development Approval: May 2016 (Actual)
GMP Approval: July 2016 (Actual)
Construction Start: August 2016 (Actual)
Construction Completion: December 2018 (Projected)
Occupancy: Fall 2018 (Projected)

Bruce and Gloria Ingram Hall with a TPC of $120 million and a total size of 166,851 GSF, is substantially complete.  Classrooms were used in fall 2018.  The contractor addressed steel work design deficiencies that were identified.

Status:  Partial occupancy began in July 2018 to accommodate classes by August 2018.  The project is complete.  A Temporary Certificate of Occupancy was issued December 7, 2018.  The remaining faculty and staff from Supple Science and RF Mitte moved into the building on December 10, 2018.  The project has received Final TCO.

Next Milestone: The next milestone will be Project Close Out and Final Report to System.