Skip to Content

Bruce and Gloria Ingram Hall

Bruce and Gloria Ingram Hall

Programmer: Facility Programming and Consulting
Architect: Treanor Architects
Total Project Cost (DD): $120,000,000
Total Project Cost (CIP): $120,000,000    
Contractor CM@R: SpawGlass Construction
Design Development Approval: May 2016 (Actual)
GMP Approval: July 2016 (Actual)
Construction Start: August 2016 (Actual)
Construction Completion: December 2018 (Projected)
Occupancy: Fall 2018 (Projected)

Bruce and Gloria Ingram Hall with a TPC of $120 million and a total size of 166,851 GSF, is approximately 96 percent complete and is already being utilized for classroom space.  The contractor addressed recent steel work design deficiencies identified.

Status:  Partial occupancy began in July 2018 to accommodate classes by August 2018.  Work continues on the remaining portions of construction.

Next Milestone: The next milestone will be Substantial Completion for the entire building in December 2018.