Skip to Content

Roy F. Mitte Space Reconfigurations

Roy F. Mitte Building Space Reconfigurations

Programmer: Facility Programming and Consulting
Architect: Brown Reynolds Watford (BRW), Dallas, TX.
Total Project Cost (TPC): $6,500,000
Total Project Cost (CIP): $9,600,000
Contractor (JOC/CSP): Sullivan Contracting/Noble General Contractor
Design Development Approval: May 2019 (Actual) 
Construction Start: December 2019 (Actual) 
Construction Completion: August 2020 (Projected)
Occupancy: August 2020 (Projected)

The Roy F. Mitte Building Space Reconfigurations project, with a TPC of $6.5 million, will repurpose vacated spaces for programs that relocated to Ingram Hall.

Status: Phase I work was initiated with the use of a Job-Order Contactor in December 2019 and is 90% complete. Phase II commenced work in February 2020 and is 25% complete.

Next Milestone: Complete Phase I work in May 2020. Complete Phase II work in August 2020