Skip to Content

Roy F. Mitte Space Reconfigurations

Roy F. Mitte Building Space Reconfigurations

Programmer: Facility Programming and Consulting
Architect: Brown Reynolds Watford (BRW), Dallas, TX
Total Project Cost (DD): $7,500,000
Total Project Cost (CIP): $9,600,000
Contractor CSP: TBD Design Development
Approval: May 2019 (Actual)
CSP Approval: December 2019 (Projected)
Construction Start: January 2020 (Projected)
Construction Completion: June 2020 (Projected)
Occupancy: July 2020 (Projected)

The Roy F. Mitte Building Space Reconfigurations project, with a TPC of $7.5 million, will repurpose vacated spaces relocated to Ingram Hall.

Status: Design development was approved for the Roy F. Mitte Building Space Reconfigurations during the May 2019 Board of Regents meeting. Following Design approval, the CMR submitted a draft GMP showing the project over budget.  In order to maintain the project schedule, work is proceeding utilizing alternative delivery methods.  Construction is scheduled to start in November 2019 using a Job-Order-Contract and completion in July 2020 following solicitation of Competitive Sealed Proposals.

Next Milestone: Contractor selection and start construction.