Skip to Content

Campus Potable Water System Upgrades

Campus Potable Water System Upgrades - Delegated Project

Engineer: Kimley-Horn (Civil)    
Contractor: JT Vaughn Construction (Water Line Extension), The Fence Lady (Jackson Hall Pump Site), TBD (Elevated Tower Rehabilitation)    
Design Stage: Construction Documents        
Est. Cost: $6,000,000
Est. Completion: 2023, based on 3-phases

This project involves the cleaning of the interior and exterior of the existing elevated water tower on the San Marcos Campus, making repairs as required, and re-painting the tower. Construction documents are complete. However, based on the results of a water modeling report and the need to install larger pumps, a new water line from Holland Street is required to meet the water demands during construction. Revised construction documents are being finalized, along with permitting required by the City of San Marcos. 

Status: Construction documents are under review, and comments are being addressed with the City of San Marcos.

Next Milestone: Bidding Phase.