Texas State University Logo
adjust type sizemake font smallermake font largerreset font size

Campus Construction

The University is making additions and improvements to better your experience at Texas State. The following list of projects, which are in various stages of development, represent over $585 million in current and future investments.


Updated November 17, 2011 (Click project name for details)

Project Cost ($) Status
Alkek Library Learning Commons 2,500,000 Consultant selected for Feasibility Study
Alumni Visitors Center Phase I 4,990,825 The project is on hold pending funding
Aquatic Ecosystem Restoration at Aquarena Center 2,509,214 Pending Army Corps of Engineers Notice to Proceed 
Bobcat Stadium-North Side Complex
33,000,000 Construction 27% complete
Bobcat Trail Mall Redevelopment 5,488,888 On hold pending completion of the Performing Arts Center projects

Brogdon Hall Renovation

7,000,000 On agenda for Nov. 2011 BOR meeting
Campus Bike Path: Spring Lake 1,883,535 The project is on hold pending resolution of funding issues with TxDOT.
Center for Research and Commercialization 6,950,000 Site excavation underway

Commons Renovation

7,210,000 CM@R selected, GMP submitted to TSUS
Electrical Infrastructure Upgrades 11,800,000 Design is 100% complete
Engineering and Science Building 82,265,414 Estimated cost adjusted
Housing and Residential Life Office Building 12,166,000 Construction 3% complete
Lampasas Hall Renovation 3,300,000 Construction 5% complete
Music Building 56,705,000 Estimated cost adjusted
North Campus  Housing Complex 46,125,712 Construction ~65% complete

Performing Arts Center (PAC)

Music Recital Hall and Theatre Center

Parking Garage

South Chill Plant

Streets and Grounds Improvements

83,243,646 Site excavation, drilling piers, installation of the tower crane, structural steel erection in progress
Psychology Renovation 8,595,436 Final programming report to be submitted by December, 2011
RRHEC (#3) - Health Professions 1
48,820,000 Estimated cost adjusted
RRHEC Building (#4) - Health Professions 2 31,900,000 Estimated cost adjusted
River Center Education and Research Facility 7,000,000 Programming will commence when funds are available
South Campus Utility Upgrades 6,000,000 Design is 100% complete; CM@R selected; GMP under review
Tomas Rivera Drive Relocation and Student Center Drive Realignment 8,731,938 Final phase to be coordinated with the North Campus Housing Complex project
Undergraduate Academic Center
47,700,000 Construction is 50% complete
Utility Upgrades Bobcat Trail 3,500,000 Design will commence in late FY2012
West Campus Residence Life Housing 56,147,345 Programming is 50% complete

 

_